HS2 Notification: Works to set up Westgate site, December 2020 and early 2021

We will be building a ventilation shaft and headhouse at our Westgate site from 2 December and during early 2021. SCSJV will start works to set up the Westgate site. The main works will involve:

  • Installation of worksite fencing, gates, and security
  • On-site surveys and inspections
  • Installation of monitoring equipment
  • Vegetation and site clearance within the site boundary
  • Piling works
  • Bulk excavation of material
  • For further information please see our works notification.