Update: Installation of electricity cables

Our recent notification advised that works would be ongoing during January to June 2021. Works are required for excavation of a cable trench within the HS2 SCS site at Canterbury Road during the weekend of the 20/02 & 21/02. The area will be fenced off and acoustic barriers will be installed to limit noise impacts. Works will be undertaken on the following dates

Saturday (20/02/21)

• Excavate cable trench within site boundary

• Install ducts within trench

• Backfill trench with sand & stone

Sunday (21/02/21)

• Concrete trench

• Remove spoil

For further information please see our update works notification.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk .

Posted on 9th February 2021

by HS2 in Kilburn and Northolt